The Community Association's biggest approved lake project this year was a retaining wall at Donnie's Point, capped at $345,000. The barges and floating platforms out on the water were working for someone else. Public Water Supply District No. 2 of St. Charles County closed out 2026 contracts worth a combined final value of close to $7 million to inspect, clean and reline the sanitary sewer mains that run under the lakes. That is about twenty times the wall's cap.
The work that drew the most attention came from a utility doing maintenance under the lake bed. Most of it is now finished. The rest of the year's lake work came from the Community Association's own projects, and those are smaller and still in progress.
What the barges were doing
The district's sanitary sewer system for Lake Saint Louis sits "under the small and large lakes," as its own capital plan puts it. Those pipes can't be reached from a street. In a March 12, 2026 board memo, district staff said that after a first round of inspection, several segments needed heavy cleaning and a second look. They described the setup this way:
"The scope of work requires the use of several barges, floating platforms, and support structures positioned on the lake to facilitate placement of caissons and support the cleaning and inspection operations."
Two contractors split the job. Inspect.AI cleaned and re-inspected 19,060 linear feet of under-lake sewer main and supported the lining crews on the water, including bypass pumping. SAK Construction's proposal covered seven under-lake lines, 8 to 12 inches in diameter, to be relined with cured-in-place pipe. That method puts a new liner inside the old pipe so nobody has to dig it up. The plan called for about 6,786 linear feet of lining.
Two memos in the district's October 22, 2026 board packet close out both contracts:
- Inspect.AI: done. A final deduction of $307,230 for bypass work that wasn't needed brought the final contract to $4,626,790.
- SAK Construction: "The 2026 Sewer CIPP Lining under Lake St. Louis is now complete and has been put back into service." One segment didn't need lining after all once crews watched the pre-lining video, so $346,600 came off. The final contract was $2,367,777.20.
The schedule ran long. A June board packet expected the inspection work to wrap up by the end of June. The closeout memo is dated October 8. As late as its September 1 meeting, the Community Association's Lakes & Parks Committee reported that work was continuing with the district "to assure their lake access results in minimum impact on membership lake usage."
The Community Association's own lake work, by comparison
Next to the sewer contracts, the Association's two lake projects for 2026 look small in dollars. They're the ones paid for out of the Association's budget, though, and they're the ones still open.
| Project | Who runs it | Contractor | Money on record | Status in the latest posted records |
|---|---|---|---|---|
| Under-lake sewer inspection and cleaning | PWSD No. 2 | Inspect.AI | $4,626,790 final | Complete, per Oct. 8 memo |
| Under-lake sewer lining | PWSD No. 2 | SAK Construction | $2,367,777.20 final | Complete and back in service, per Oct. 22 memo |
| Donnie's Point retaining wall | LSLCA | Stutz Excavating | Not to exceed $345,000 without further Board approval | Approved July 28; no start date posted |
| Lower Dauphine Cove dredging | LSLCA | Not named in minutes | Not stated in minutes | Set to resume after Labor Day |
Donnie's Point is the Association's pavilion site that used to be called Jefferson Point. The wall going in there is sheet piling, which is a retaining wall and not a dam or spillway repair. The Engineering & Facilities Committee recommended engineering oversight for the job, pointing to its life-safety implications and its cost. It suggested Shannon & Wilson for testing and construction supervision and favored a lower-cost option known as SZ22. Those were committee recommendations, and the posted minutes don't show a final Board vote on them.
Dauphine Cove's dredge ran into the same kind of delay
The sewer contractors weren't the only crews on the lake whose schedule slipped. At its February 24 meeting, the Board reported lower Dauphine Cove closed for dredging, with completion expected in early May. By April 28, work had only just started. The new target was mid-June, and boating and skiing in the cove were off-limits until the dredging was done.
The May 5 Lakes & Parks minutes explain the delay. Cavitation in the pump-out system, along with logs and other debris, cut into how well the silt-removal equipment worked. By August 3, the Engineering & Facilities Committee said dredging would carry on past Labor Day. It raised the idea of extending the contract to more areas once the main area was finished, which could save the cost of moving equipment out and back in later. The committee also noted a possible discrepancy in the original dredging survey that needed to be reconciled. The September 1 committee report repeats that the cove's dredging would resume after Labor Day.
The Association posts minutes only after they're approved. As of late October, the minutes page listed July as the latest linked Board minutes. So any update on the cove, the Donnie's Point start date, or decisions from the October 27 Board meeting will show up there in the coming months.
What changes on the surface from November 1
With the district's barges finished, the off-season on the water follows the Association's own calendar. The October 2026 newsletter and recent committee minutes set out the sequence:
- October 11: The gas dock had its last day of the season. Starting that day, boat inspections and boater safety classes are by appointment through Water Patrol at 636-625-3120, option 9.
- After October 11: The Dam Bar closed for the season.
- November 1: The kayaks are put away, outdoor pavilion rentals end for the season, and the golf course goes walk-only with no carts.
- November 1 through April 1: The clubhouse runs winter hours, opening at 8 a.m.
The gas dock closing doesn't end the boating year. The Association's Lakes & Parks rules set the boating and registration season as April 1 through March 31. If the lakes freeze, the same rules say motor-driven conveyances aren't allowed on either lake, and they describe ice skating as not recommended and at the individual's own risk. The posted rules document is the October 22, 2024 revision, so the full rules are worth checking against any later notice from the Association. This is a general summary, not legal advice, and the Association office is the right place to confirm how a rule applies to your boat or dock.
A few smaller changes are also on the way. Water Patrol reported that the Windjammer Point courtesy docks will move to the end of the docks, where they're easier for members to use when visiting. The Association is also updating its website and introducing an app.
The small lake's turn comes in 2028
The district's sewer work under the lakes isn't over for good. The same October 22 packet that closed out this year's contracts includes a capital plan entry called "Lake Saint Louis Small Lake Sewer Cleaning." It explains that periodic inspection and maintenance of the under-lake system is needed "to assure the system operates correctly and to avoid a potential failure."
The plan has design in 2027 with a $250,000 budget and construction in 2028 with a $1.75 million budget. The scope is to install new manholes at the lake junctions to reach the system, then jet-clean and video-inspect the mains. A capital plan is a budget forecast and can change before construction starts. Still, it shows the district plans to return to the lakes, and the 2028 project is planned around the small lake.
That timing overlaps with the Association's own long-range planning. In September, the Lakes & Parks Committee heard a presentation on the Association needing more revenue starting in 2028 and on restructuring its capital expense rules. The Finance Committee also started work on the 2027 budget that month. So 2028 could bring utility crews back on the water at the same time the Association is changing how it pays for its own lake projects.
If you own on the water and wonder how this year's work and the projects ahead might come up when you sell, or when you buy near the lake, The Lisa Adkins Team follows these Association and district decisions closely and can walk you through what they mean for a specific property. Schedule your free consultation.